Want another way around downtown Kingsville?
That's one goal of the Heritage Road extension. The plan is to build a new street north from Main Street West toward Road 2 West.
Much of that route follows Fox Lane. In 2024, the Town's engineers called it a one-lane farm access road made of gravel and earth, about 1.8 kilometres long.
The new street would have two lanes: one in each direction.
The project has a $14 million budget. But there's a question the records we checked don't answer:
When can you drive the new road all the way to Road 2 West?
What are we getting?
In August 2026, Council voted 6–0 to award the road contract. One member was absent. J&J Lepera Infrastructures had the lowest of five bids: $8.844 million before HST.
The work includes:
- Traffic lights at Main and Heritage
- The new road heading north
- Sidewalks and a separate bike path
- Street lights, trees and sewers
- Work to collect and manage rainwater
Why lights instead of a roundabout?
Engineers found both would handle traffic about as well. But a roundabout would cost much more. It would need more land, more work to move utility lines and more construction.
The Town scheduled the first stage for Oct. 5, 2026, weather permitting. On Oct. 20, AskKingsville's publisher saw the route north of Main blocked off, with trucks working on site. That puts work underway by Oct. 20; it does not confirm the actual start date. A second stage is planned for early 2027. Staff aim to finish the contract work by the end of 2027.
Finishing this contract does not give us a confirmed opening date for the whole route.
Look at where the map stops

Town design map from the Aug. 17, 2026 report.
Follow the red line north. It stops before Road 2 West.
The 2024 study said the last stretch and the Road 2 West intersection would be designed by "others" and finished later.
That was the plan in 2024. The study and map don't tell us who is responsible today. The records we checked don't give an opening date for the full route.
Would that last piece cost the Town more?
We don't know. A developer or someone else could build it under a separate deal. The Town could pay for it later. Or it could be covered by money already set aside.
Those are possibilities, not confirmed plans. We haven't confirmed who pays or whether the last piece is inside the $14 million budget. The map alone doesn't mean another bill is coming.
Who pays the $14 million?
The road contract is part of the budget. The rest covers land, design work, moving utility lines and other work.
The August 2026 staff report lists:
- $6.5 million from the Province
- $650,000 in federal funding
- $6.85 million the Town plans to borrow
Almost half would be borrowed.
The plan is to repay that loan, plus interest, with development charges. Those are fees builders pay when they build. Council told staff to apply for a loan. We haven't found a signed loan in the records we checked.
There is a risk worth explaining.
In February 2024, staff warned that taxes and water rates might have to cover debt payments if those fees didn't return to 2020–2022 levels.
That warning was about the road and water main together. It was not a new warning about the 2026 road contract.
In August 2026, staff expected the project to stay within $14 million. That is an estimate, not the final bill.
Why a road story is also a water story
Three Councils. One road project.
The 2018–2022 Council backed the idea in March 2021.
The 2022–2026 Council awarded the road contract in August 2026.
The 2026–2030 Council will oversee the Town's remaining work during its term.
The current Council took office in November 2022. All eight votes listed below belong to its term.
Part of a new large water pipe was planned along the road route. Staff said southwest homes could have low water pressure at busy times. The area also lacked a backup supply if certain pipes failed, and enough water capacity for new housing.
In October 2023, Council voted 6–1 to delay the road and water main. Staff were worried the Town would borrow money that future builders' fees might not pay back.
In early 2024, a new provincial water grant opened. Council then approved steps on land, design, a grant application and deals for developers to pay fees early. We haven't confirmed those early payments happened.
Staff aimed to start the combined project in September 2024. The records don't fully explain the later road schedule.
The Town says the water-main section along the road was finished in 2025. That doesn't mean the whole southwest water project was done. The road contract followed in August 2026.
What should we follow next?
How is work progressing? Who builds the last piece? Who pays for it? When can you drive the whole route?
The next Council's term starts Nov. 15, 2026. It will oversee the work left during its term.
Which question matters most to you?
Related: Who actually runs Kingsville?
Supporting details
These details, votes and sources are additional to the four-minute story above.
Two grant figures
The Province announced a $7,437,500 road-grant award in January 2025. The 2026 budget sets aside $6.5 million in grant funding. The award and the amount listed in one year's budget are different measures. The records we checked don't explain the difference. They don't show that the grant was cut. The water-grant opportunity discussed in 2024 was a separate program from the road grant announced in 2025.
Land and earlier decisions
In April 2023, staff said construction was expected in 2024. In October 2023, Council directed correspondence about development-charge changes to the housing minister, local MPPs and every Ontario municipality.
The February 2024 report said certain road lands "were discovered to be without any legal owner." The Town obtained a court declaration of ownership. Council later awarded the corridor water-main contract for about $1.95 million in 2025.
Under a 2024 land deal, if the road isn't built by 2027, the Town would pay the owner of 258 Main Street West fair market value for the land it took. We haven't confirmed whether that deal was later changed.
The existing Heritage Road
The first 500 metres or so south of Main, to about Dieppe Crescent, is a Town-owned connecting link despite its County Road 50 sign. The County maintains it under a cost-sharing agreement. Its 2024 asset plan says the County pays 80.6% of routine upkeep on that stretch. That share does not cover rebuilding. Main Street at the intersection is also a Town connecting link.
Farther south, Heritage Road is a County road. The County and Town are jointly studying improvements between 690 Heritage Road and Lake Drive; the reviewed records don't establish a funded construction schedule. The County study page lists contacts at both governments.
How Council Voted
| Motion | Date | Moved by | Seconded by | Result | For | Against | Other |
|---|---|---|---|---|---|---|---|
| Delay the southwest transmission watermain and collector road pending development-charge clarification and/or pre-payment agreements | Oct. 10, 2023 | DeYong | Lowrie | Passed 6–1 | Rogers, DeYong, Jarvis-Chausse, Lowrie, Neufeld, Patterson | Gaffan | — |
| Add one more developer's early-payment deal | Feb. 12, 2024 | Patterson | Neufeld | Passed 7–0 | All seven | — | — |
| Restart: land, grant, study, builders pay fees early | Feb. 12, 2024 | Patterson | Gaffan | Passed 6–0 | Rogers, DeYong, Gaffan, Lowrie, Neufeld, Patterson | — | Jarvis-Chausse abstained |
| Endorse the environmental study | June 24, 2024 | Jarvis-Chausse | Lowrie | Passed 7–0 | All seven | — | — |
| Award the corridor watermain contract and seek financing for southwest watermain phases 1 and 2 | June 16, 2025 | Patterson | Lowrie | Passed 6–0 | Rogers, DeYong, Gaffan, Lowrie, Neufeld, Patterson | — | Jarvis-Chausse absent |
| Expropriate land for the Main/Heritage intersection | Jan. 19, 2026 | Patterson | DeYong | Passed 5–0 | Rogers, DeYong, Gaffan, Jarvis-Chausse, Patterson | — | Lowrie, Neufeld absent |
| Shared stormwater infrastructure agreement | Mar. 9, 2026 | Patterson | Gaffan | Passed 7–0 | All seven | — | — |
| Award the construction contract (Res. 157-17082026) | Aug. 17, 2026 | Jarvis-Chausse | Lowrie | Passed 6–0 | Rogers, DeYong, Jarvis-Chausse, Lowrie, Neufeld, Patterson | — | Gaffan absent |
Where the Public Record Stops
- Whether construction began on the scheduled Oct. 5, 2026 date.
- The opening date for the full route to Road 2 West, including the northern section assigned to others in the 2024 study.
- Whether developers actually prepaid their fees by the 2024 deadline.
- The final financing terms and final project cost.
- The accounting difference between the $7,437,500 road-grant announcement and the $6.5 million in the 2026 budget.
- A full explanation of the road timetable after the September 2024 target, and any later changes to the 2027 land-deal term.
- Any funded construction schedule for the separate County Road 50 study area.